A commercial solar inverter commissioning checklist should produce evidence that the installation matches its design, uses approved protection and control settings, and behaves correctly under representative operating conditions. Complete document review and de-energized checks before controlled startup, then verify metering, operating functions, monitoring and handover records.
This checklist is a project acceptance framework. Qualified personnel must apply the exact equipment manual, approved test plan and local electrical requirements; test voltages, switching sequences and protection limits are model-specific.

1. Establish the acceptance criteria
Before mobilizing, agree who may authorize energization, who witnesses each test and what constitutes a pass. Record project identity, site location, serial numbers, firmware, drawing revisions and applicable utility approvals.
| Check item | Result or evidence |
|---|---|
| ☐ Approved single-line diagram and final equipment schedule are available. | __________________ |
| ☐ Cable, protection, earthing and export-control designs are approved. | __________________ |
| ☐ Current installation manuals match the installed model and revision. | __________________ |
| ☐ Utility settings and any witness-test requirements are documented. | __________________ |
| ☐ Instruments have suitable ratings and current calibration records. | __________________ |
Deye’s SUN-60/70/75/80K-SG02HP3-EU-EM6 product page identifies a three-phase hybrid family. Its published battery voltage range is 160–1,000 V. Include battery and backup-function checks when these features are installed and within the project scope. An input voltage range alone does not establish battery compatibility.
2. Complete de-energized installation checks
Use the approved isolation procedure and verify the installation is safe for the intended inspection. Record findings against equipment identifiers so defects can be closed out.
| Check item | Result or evidence |
|---|---|
| ☐ Mounting, enclosure condition and service clearances match the manual. | __________________ |
| ☐ Cable support, glands, weather sealing and segregation are satisfactory. | __________________ |
| ☐ Protective conductors and bonding are verified. | __________________ |
| ☐ Termination torque is recorded against manufacturer requirements. | __________________ |
| ☐ AC phase identification, neutral arrangement and protective devices match the design. | __________________ |
| ☐ PV strings are identified, polarity is verified, and voltage is checked against cold-weather design limits. | __________________ |
| ☐ Surge protection and isolator labels match the drawings. | __________________ |
Perform insulation tests only using the approved method, isolating inverters and sensitive electronics as required. Do not apply an insulation tester through connected equipment simply because it appears on the same circuit.
3. Verify metering before enabling export control
Check current-transformer (CT) location, ratio, direction and phase mapping, plus meter addressing and communications. Use a known, stable load condition and compare readings with an independent instrument.
Record per-phase voltage, current, active power and import/export direction. Investigate implausible readings before enabling automated controls. Correct total power alone does not prove that every phase is mapped correctly.
Where zero export is required, agree the measurement point, permitted response and acceptance method with the designer or utility. Test changing load and PV conditions, including loss of the control measurement. A zero-export setting is not evidence of verified performance.

4. Apply approved settings and start under control
Follow the model-specific startup sequence. Confirm voltage and frequency limits, protection profile, active-power limit, reactive-power mode and reconnection behavior against the approved settings schedule. Save an export or screenshots for the handover pack.
For projects using the Deye SUN-40/50K-SG01HP3-EU-BM4 models, verify the exact installed variant and any parallel-control configuration. The page’s model table lists these 40/50 kW variants as BM4, with a 160–800 V battery range, distinct from the EM6 range above. Use the installed model’s limits and approved battery list; do not copy settings between families.
For hybrid systems, record battery compatibility, battery management system (BMS) communications, charge/discharge limits, state-of-charge reserve and operating schedules. Test generator or backup interfaces only where designed, installed and authorized.

5. Witness functional tests and record results
| Test | Evidence to retain |
|---|---|
| Initial operation | Startup log, alarms and stable operating readings |
| PV tracking | String or tracker readings interpreted against irradiance and temperature |
| Export or power limit | Time-series response at the agreed measurement point |
| Reactive control | Setpoint and independently measured response |
| Grid-loss response | Approved test method and witnessed result |
| Hybrid functions, if included | Charge/discharge and transition records |
| Communications failure | Alarm and approved fallback behavior |
Do not infer anti-islanding compliance from an improvised breaker-opening test. Use the locally approved procedure and required certification or witness evidence.
6. Close the project with usable operating records
Retain as-built drawings, settings backups, test results, photographs, training records and an open-defect register. Verify timestamps, alarm delivery and monitoring access. Confirm the operator knows normal readings, escalation contacts and the approved shutdown procedure.
Agree a follow-up review under representative weather and load conditions if commissioning-day conditions cannot demonstrate full operation. Record any deferred tests explicitly.
Use a commissioning record that supports repeat testing
A useful record makes results traceable to the conditions under which they were measured. Avoid a worksheet containing only a row of ticks: it gives the operator little help if a problem appears after handover.
| Record field | Why it matters |
|---|---|
| Equipment and test identifier | Connects the result to one asset and procedure |
| Acceptance criterion | Shows the approved basis for pass or fail |
| Instrument and calibration reference | Establishes how the reading was obtained |
| Load, irradiance and temperature | Helps explain limited output or deferred testing |
| Measured result and settings revision | Allows comparison after a software or configuration change |
| Witness, date and defect reference | Provides accountability and a route to close issues |
For example, an export-limit test should state the load change applied, the measured PCC response and the applicable acceptance criterion. A photograph of the inverter’s power-limit setting cannot show whether the meter was positioned correctly or the control loop responded as intended.
Divide outstanding items into defects requiring correction before energization, defects preventing operational acceptance and minor documentation actions, using the project’s approved process. Do not let an administrative handover obscure an unfinished functional test.
After any firmware update or material settings change, assess which acceptance tests need repeating. Retain the earlier results and configuration rather than overwriting them, so later troubleshooting can distinguish an installation issue from a subsequent change.
Frequently asked questions
Is the inverter’s normal indicator enough for acceptance?
No. It establishes only a limited operating state. Acceptance also needs verified wiring, metering, settings, protection evidence, functional performance and complete records.
Can one checklist cover string and hybrid inverters?
A common framework can cover documentation and basic inspection. Hybrid projects need additional battery, energy-management and backup or generator tests where applicable. Use model-specific test steps.
What should happen when a test fails?
Record the failure and affected equipment, make the installation safe where necessary, correct the cause and repeat the relevant test. Close acceptance only after the evidence meets the agreed criteria.
Prepare a complete commissioning scope
To prepare a model-specific commissioning plan with Deye’s support team, send:
- Inverter schedule, firmware versions and single-line diagram.
- Battery, generator and parallel-operation scope, where applicable.
- Utility acceptance requirements and planned witnessed tests.
Request the current manuals and approved test documentation before mobilization.